Histograms for Different Resources

Shahzad SikandarMember for 20 years 8 months
Created
5
6
0
It is possible to view histogram for diffrenet resource in resource usage profile?

I meant to ask, i want to see comparision of differnt resource as a histoigram on each activity, cuz p3e only show resoule profile for single resouirce to be seen individually.

any comments, please
be appreciated.

thanks

5 replies

Oldest first
  1. 0
    Kevin Button ·
    You could try using the Stacked Histogram, however a problem using this is that it shows individual resource usage based on the currently filtered activities rather than the selected activities.

    HTH

    Kevin
  2. 0
    Shahzad Sikandar ·
    but when you checked on staked histograme every thing disappeared.
  3. 0
    Kevin Button ·
    You need to right click on the graph and select ’Resource Usage Profile Options’, where you need to set some filters and choose a colour for each filter output.

    Cheers

    Kevin
  4. 0
    Shahzad Sikandar ·
    many thanks for your reply,
    but there is no filter selection option under resource usage profile GRAPH OPtion, I am using Projection Management Software (P3e).
  5. 0
    Shahzad Sikandar ·
    i have got that done now.
    many thanks