Relationship Links not displaying

Nigel WinkleyMember for 20 years 5 months
Created
2
3
0
Hi all

Had an odd one the other day. Selected the Critical Filter and then, using Goto, added a few other activities to show the relationship between critical activities and some non-critical activities.

Switched the Show Links on. P3e only showed the links for the original filter - i.e. the critical activites not the ones that I had just added.

Tried a different filter and did the same sort of thing. Same result.

Logged it with Primavera and was told that this is a known problem.

So if anyone has the same sort of thing, you will now know why. Odd one though...

2 replies

Oldest first
  1. 0
    Richard Rowberry ·
    Nigel,

    I’ve had this problem on many occasions - the only way i get round it (but it is a pain) is to feed back to whichever activities you need, code them all with a UDF (including those from the original filter), and then re-run the filter to pick up the UDF code. OK if your schedule remains unchanged, but if it’s moving every week or month, then you’re going to have to re-code activities.

    Not great, but it does for now...

    Richard
  2. 0
    Richard Rowberry ·
    Nigel,

    Instead of the UDF answer, there is another way. If you trace through to as many links as you need, then go to the activity details dialogue box, select predecessors or successors, and then change a lag from say zero to 5. The change it immediately back again to zero - hey presto, all your links are displayed.

    They never show you that in the user manual..

    Regards

    Richard