Global Change

Paul NaughtonMember for 20 years 3 months
Created
1
1
0
I’m trying to run a global change to copy activity code values to UDF’s so I can export them to MPP format (as I understand it is not possible to export activity codes).

I have set up the following change:

Phase UDF = Phase

Where Phase is the activity code and Phase (UDF) is a text UDF. When I run the change I am getting blank values.

What am I doing wrong?

1 reply

Oldest first
  1. 0
    Nigel Winkley ·
    Paul

    I have the following which works

    In the top section headed IF I have "Where" and then all other fields blank.
    Under the section THEN I have Parameter as ActIDNo, IS =, Activity ID. This uses a UDF I created called Activity ID.

    This GC adds the Pe3 activity ID into the UDF quite happily.

    RSVP if problems and/or PM me and I will send a screen shot.

    Cheers

    Nige