actualizer.exe

Marcio SampaioMember for 20 years 11 months
Created
2
4
0
Hello all;

Do u know the aplication of this file that is part of SDK Utilities 3.5.1??

Regards.

Marcio Eduardo

2 replies

Oldest first
  1. 0
    Bill McMichael ·
    Actualizer is a program that will create timesheet records after the fact. It is useful if you want to use Timesheets and activities already have actuals.

    Regards,
    Bill
  2. 0
    Marcio Sampaio ·
    Bill,

    Thanks a lot for your response.

    Regards.

    Marcio Eduardo