Skip to content

change of WBS when Importing P3 to P6

James bidMember for 17 years
Created
3
1
0
Good Day Planners!

May I ask your help regarding my problem in importing because whenever I import a program from P3 to P6, The Project ID at P3 automatically included in WBS code at P6. here what was happened...
in P3
Project ID Project Description
CP00 Construction Project 00

WBS(sample only)
BCA Briton Construction and Partners

in P6 (after importing)
WBS (sample only)
CP00.BCA Briton Construction and Partners

All the "CP00" was added to all WBS Code of the Project..
May I know what was the problem.

Thank you

Chris





3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Chris

    This is by design. The first level of the WBS is the project itself. If You’ll show the WBS, the complete path will be shown. Alternative: Just show WBS-Name.

    Regards
    Dieter
  2. 0
    James bid ·
    Thanks Dieter!

    May I know how to hide the WBS Code? or just say Show only WBS name.

    Because what the problem is upon I imported the program with the project ID CP00 to P6 The WBS was turned to CP00.BCA instead of BCA only
  3. 0
    Dieter Wambach ·
    Chris

    View Activities: You have the columns
    - WBS; shows the complete hierarchy
    - WBS Name; Shows the name of that WBS-node
    - WBS Path; Shows the code without the upper nodes
    For you WBS Name or -Code I assume then it will be shown with each activity.

    Summary lines: Group & Sort: Group By WBS, unmark: Show ID Code

    Regards
    Dieter

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?