Printing Calendars
In the Open Standard
Nigel WinkleyMember for 20 years 5 months
- Created
- 8
- 4
0
Hi All
Cannot seem to be able to print calendars. Spoke to helpdesk, they agree! Knowledge Base 11860 refers.
If anyone else wants to be able to print calendars, I suggest that they log a call with the helpdesk as the more calls the better the chance of getting something corrected.
Seems a fundamental error to me - all other packages I have used let you print out a calendar. When you are merging projects and have tens of calendars I would have thought it was a fairly basic requirement.
So there you go. Don’t sit back and think "it will be added later by someone..." ring the helpdesk and ask them to get it added. The more people that do the better - and not just for this but any missing function. Forget workarounds get Primavera to do something - remember how much P3e costs!!!
Cheers
Nige
Cannot seem to be able to print calendars. Spoke to helpdesk, they agree! Knowledge Base 11860 refers.
If anyone else wants to be able to print calendars, I suggest that they log a call with the helpdesk as the more calls the better the chance of getting something corrected.
Seems a fundamental error to me - all other packages I have used let you print out a calendar. When you are merging projects and have tens of calendars I would have thought it was a fairly basic requirement.
So there you go. Don’t sit back and think "it will be added later by someone..." ring the helpdesk and ask them to get it added. The more people that do the better - and not just for this but any missing function. Forget workarounds get Primavera to do something - remember how much P3e costs!!!
Cheers
Nige
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?