P3 e/c Baseline

Karim MounirMember for 20 years 6 months
Created
2
1
0
Hi,

If i didn’t make a baseline in a schedule (eg. didn’t convert another schedule to be the baseline nor made a copy of the current schedule to be the baseline ), then P3 e/c assigns the current schedule to be the baseline, OK.

Then the target activities dates should be the same as of the updated dates of the ongoing activities, right ?

This isn’t right for the ongoing activities or completed activities, only works with te activities which didn’t start till the data date, CLAIRFY please!!

2 replies

Oldest first
  1. 0
    Steven Oliver ·
    P3e uses the fields Planned Start and planned Finish as the basis of the baseline. This works fine for activities with no progress, but not so good for completed and especially in-progress activities.

    Use Global Change to set Planned Start/planned Finish equal to Start/Finish.
  2. 0
    Karim Mounir ·
    thanx