Relationship Lines
In the Open Standard
Paul NaughtonMember for 20 years 3 months
- Created
- 3
- 3
0
Hi guys,
Forgive me if this is a bit basic but I’m still trying to make P3e do what P3 does.
In P3 if I want to create a storyboard I’ll pick an activity (usually a completion milestone of some description) and trace through the predecessor logic to create the critical path. I can then take a picture with or without the relationship lines and reorganise the data to suit requirements.
In P3e I understand I cannot take the picture but should be able to do everything else.
When I try to display the relationship lines nothing appears, I note from using other filters the facility is working fine for everything already filtered but won’t include any activities added. Does anyone know a way to rectify this or will I need to code up each path each time and then run a filter?
Paul
Forgive me if this is a bit basic but I’m still trying to make P3e do what P3 does.
In P3 if I want to create a storyboard I’ll pick an activity (usually a completion milestone of some description) and trace through the predecessor logic to create the critical path. I can then take a picture with or without the relationship lines and reorganise the data to suit requirements.
In P3e I understand I cannot take the picture but should be able to do everything else.
When I try to display the relationship lines nothing appears, I note from using other filters the facility is working fine for everything already filtered but won’t include any activities added. Does anyone know a way to rectify this or will I need to code up each path each time and then run a filter?
Paul
3 replies
Oldest firstLog in or join to reply