P3e updating with labor units
In the Open Standard
Yves TrudelMember for 21 years 2 months
- Created
- 1
- 2
0
Hi everyone, I’m new to P3e and I have created a file with labor units, but no resources or roles. I was expecting to retrieve P3 3.1 option to set a percent complete and have the associated labor units updated without changing the "at completion" quantity. All I get is that the "at completion" quantity changes, but not the actual. What am I doing wrong?
Thanks in advance
Yves Trudel
Thanks in advance
Yves Trudel
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?