Skip to content

P3e updating with labor units

Yves TrudelMember for 21 years 2 months
Created
1
2
0
Hi everyone, I’m new to P3e and I have created a file with labor units, but no resources or roles. I was expecting to retrieve P3 3.1 option to set a percent complete and have the associated labor units updated without changing the "at completion" quantity. All I get is that the "at completion" quantity changes, but not the actual. What am I doing wrong?
Thanks in advance
Yves Trudel

1 reply

Oldest first
  1. 0
    Alex Wong ·
    Yves

    YOu need to learn how to progress update an activity. The best is refer back to the user manual. Remember progress an activity have sereval different way, and you need to know which one suit your schedule

    Good Luck

    Alex

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?