Primavera P 5.0 schedule problem

Bilal MohammedMember for 19 years 9 months
Created
2
2
0
Hello Friends

Im new to Primavera P5.0. I have a problem when scheduling the project. The Early start dates of completed activities are also updated with in progress activities. I am producing reports in the layout itself. So I dont want the Early start column to be updated for completed activities. I hope somebody will have the solution. Thanx in Advance

with lots of love
Bill

2 replies

Oldest first
  1. 0
    Mk Tse ·
    Your post is better on forum "Primavera Enterprise - Teamplay / P3e & P3ec" since P5.0 is under that category.

    Anyway, select the field "Start" and "Finish" rather ES/EF
  2. 0
    Bilal Mohammed ·
    Hi mktse

    Thanx for ur reply. But for the solution, if i give start and finish for ES & EF, then the columns will be updated with actual start and actual finish

Log in or join to reply