Hello Friends

Im new to Primavera P5.0. I have a problem when scheduling the project. The Early start dates of completed activities are also updated with in progress activities. I am producing reports in the layout itself. So I dont want the Early start column to be updated for completed activities. I hope somebody will have the solution. Thanx in Advance

with lots of love
Bill

1 reply

Oldest first
  1. 0
    Kevin Button ·
    Hi

    Instead of using the Early Start column, try using Start instead. This will show the activity Early Start date until it has started, then will show the Actual Start date.

    HTH

    KB