P6.2.1 SDK Installation Problem
In the Open Standard
Glenn Dexter UbaldoMember for 17 years 4 months
- Created
- 7
- 3
0
Hello Guys,
I know this is an IT problem but it seems that our company’s IT team is not capable of solving this problem regarding the Installation of SDK. We are using licenced
P6.2.1 Client but everytime our IT is installing the SDK
it is showing.
(Bad public user name or password. Database Server Error: Login failed for user ’pubuser’.
Cannot open database "PMSDK$PRIMAVERA" requested by the login. The login failed.;)
PMDB & MMDB is working but still we are not successful when it comes to PMSDK
Our Settings is:
DATA BASE NAME
PMSDK$PRIMAVERA
DATA BASE ALIAS
PMSDK
PMDB & MMDB is working but still we are not successful when it comes to PMSDK. Guys your help would be much
appreciated.
Regards,
Glenn
I know this is an IT problem but it seems that our company’s IT team is not capable of solving this problem regarding the Installation of SDK. We are using licenced
P6.2.1 Client but everytime our IT is installing the SDK
it is showing.
(Bad public user name or password. Database Server Error: Login failed for user ’pubuser’.
Cannot open database "PMSDK$PRIMAVERA" requested by the login. The login failed.;)
PMDB & MMDB is working but still we are not successful when it comes to PMSDK
Our Settings is:
DATA BASE NAME
PMSDK$PRIMAVERA
DATA BASE ALIAS
PMSDK
PMDB & MMDB is working but still we are not successful when it comes to PMSDK. Guys your help would be much
appreciated.
Regards,
Glenn
7 replies
Oldest firstLog in or join to reply