P3e calendar and timescale help
In the Open Standard
Adele BothaMember for 19 years 9 months
- Created
- 3
- 2
0
I have activities that are delayed by 4 months or more because of work windows and I’m trying to display the bar differently. I added necking to the bar display options by clicking on the calander nonwork time under the bar settings tab, but now it also necks over weekends and my bars look like sausages. Help please. I’m going crazy. How can I get the bars to neck for my big non work windows and not for weekends.
3 replies
Oldest firstLog in or join to reply