Resource Curves

Chris CareyMember for 19 years 9 months
Created
1
2
0
I am trying to display resource curves in Primavera P3e. I have selected "Bell Curve" against the resource ID name in the activity details section. However when I move to the Resource usage profile, it doesn’t seem to make any difference to the shape of the resource. I have read the help file and have made sure that my activity is fixed durations & Units/Time. But whatever I change the resource curve to it doesn’t seem to be changing the shape of the resource! What am I doing wrong?!

Thanks

Chris

1 reply

Oldest first
  1. 0
    Kevin Button ·
    Chris

    I tried what you have done (and had to make a couple of assumptions) but I got the curve OK.

    Did you right click over the graph and untick the ‘Show All Projects’ option?

    Not sure what else the problem might be.

    KB

Log in or join to reply