Dear All,

I have a problem with P3-P5-P3 export-import:

When I import P3 file to P5 and export again to P3 in some activities in P3 accurs resource duration. Usually one day less than activity remaining duration. Also in some activities’ Budgeted Quantyties also reduces.

If somebody knows how to solve this, please share.

Kind Regards,
Aydin

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Aydin,

    Have you check your unit format and hours per time period on user preference and admin preferences. By default P5 don’t adopt imported p3 files setup so you need to make sure that P5 have the same setup before importing and exporting.

    Rodel