Skip to content

Summarization % of Base Line for P5

Omar Abdull SattarMember for 19 years 10 months
Created
2
2
0
for P5 I can not see the Summary% for the Baseline when I am trying to make comparison with the actual. By the way I can see BL Original Duration , BL Start & BL Finish Date in the Summary Band and also I can see all BL percentages for all activities except the summary band is coming Empty for WBS or Activity Code Summary.

2 replies

Oldest first
  1. 0
    Omar A.S. ·
    Dear IC Quiamco

    Yes I mean Unit% & Duration % and another things BL Remaining Duration in Summary

    Thanks

    Omar A.S
  2. 0
    Karim Mounir ·
    Hi Omar,
    Checkout this post:
    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=30849
    it may helps.

    Regards,
    Karim

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?