Skip to content

Baseline

Marcio SampaioMember for 20 years 11 months
Created
2
2
0
When u create first baseline using P5 BL Star and BL Finish = Planned Start and Planned Finish, ok?

Why Start and Finish is not also equal?

Regards.

2 replies

Oldest first
  1. 0
    David Kelly ·
    Was there any progress in your project when you made the first baseline?
  2. 0
    Hamed Planner ·
    Marcio ,


    at the time you set your currnt project as a Baseline as you mentioned
    your planned start = Base line start
    Planned Finish = Base line finish which is correct untill your first update of the schedule

    also

    as you prgress they will change ,

    They are couple of good query regarding baseline i suggest ou review them,


    Regards,

    Hamed

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?