Level of Effort and Critical Path

Sebastian RushMember for 22 years 2 months
Created
8
2
0
Hi all! I have a master schedule with a number of LEO activities, but when I schedule by using longest path as critical, they do not "turn" red??? Can someone educate me a bit on this please.

Thanks.

Seb

8 replies

Oldest first
  1. 0
    Hamed Planner ·
    Hi Seb,

    As you said you have a Level OF Effort Activity,

    Level of effort is not part o your critical path becouse its duration is defined base on your critical path Duration,
    As an example , you have a project and you have security guard on site , you could not say Security guard is part of your Critical Path, becouse the duration of Perform security task is depend on your project Duration , the same for Services , Supervision ( In some cases) , PMO Offic


    Good Luck

    Hamed
  2. 0
    Dean Mulligan ·
    Hi, I’d like to know more about establishing a critical path using LOE bars. For example in a programme that has 1000+ activities that role up to say 50 LOE’s - it may be useful to show which LOE’s are ’representing’ critical activities

    I’ve looked at creating a ’New’ LOE bar (with a filter) to go with the Remaining and Actual LOE’s - this looks tricky and may not be possible, before I waste a week doing this, has anyone else tried and succeeded????
  3. 0
    Gordon Blair ·
    Dean,

    I tend to just use the WBS, run a rolled up layout and where the WBS contains critical activities, they will show on the summary bar.

    [The benefit of P6 being that you can save the ’roll-up level’ when you save the layout]
  4. 0
    Alex Wong ·
    Hi

    LOF is same as the old "Hammock" activity, it provide the summary effort of the linked activity, however, it cannot be a critical because simply is id not form part of the detail critical path.

    To achieve what you wanted in a report format you can use coding to drive the LOE activities to turn RED color.

    HTH

    Alex
  5. 0
    Dean Mulligan ·
    Thanks guys, a colleague said I could drive the colour through coding. This is the best way forward for me now (even though I may have to revert to the WBS option - Plan B!!).

    And I am trying to do it using the Activity ID but the filter changes ALL the LOE activity colours. How can I isolate just 1 activity? Also everytime I run the filter and then go back in ALL the settings go back to "all activities" ie it loses the settings I want and goes to default ..... why is that?
  6. 0
    Dean Mulligan ·
    Gordon .... thanks for the tip on P6, it’s been quite annoying for years that a rollup has to be done again and again ........
  7. 0
    David Podmore ·
    Just a last note; have you tried using a WBS Summary task? It mimics a WBS parent without being one AND can be on the Critical Path.
  8. 0
    Dean Mulligan ·
    Interesting David, I’ll try that now

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?