EV QUESTION
In the Open Standard
Oliver MellingMember for 19 years 5 months
- Created
- 11
- 2
0
Hi,
I am doing a baseline comparison on someone elses plan.
How is it possible to have and Earned Value cost that is higher than the budgeted cost for a WBS summary level?
Isn’t the EV calculated from the activity % complete multiplied by the baseline budgeted cost?
(With performance technique set to Activity % complete)
I have the baseline assigned as the project baseline in the assign baseline dialog box.(Which I believe is the baseline EV calcs work from)
I am doing a baseline comparison on someone elses plan.
How is it possible to have and Earned Value cost that is higher than the budgeted cost for a WBS summary level?
Isn’t the EV calculated from the activity % complete multiplied by the baseline budgeted cost?
(With performance technique set to Activity % complete)
I have the baseline assigned as the project baseline in the assign baseline dialog box.(Which I believe is the baseline EV calcs work from)
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?