Baseline 2 in P3e

Minhas ShaikhMember for 19 years 6 months
Created
2
3
0
Hi Planners,
I have to make another baseline. For second baseline I opened my one of previous project and tried to current project as a baline. But unfortunatly, it didn’t go through. I removed all basline of project and after changes tried to make current project as a basline but still i found previous basline dates. I don’t know how to remove previous baseline dates . in this way current project gives me same previous basline dates.
Hope it could be understandable for everybody.

Thanks,
Minhas

2 replies

Oldest first
  1. 0
    A D ·
    Copy the baseline 1 project and then change the data date you required.

    Remove all actual start and actual finish dates. This can be easily done through global change.

    Now make the necessary changes you require.

    Hope this is clear.

    Cheers,

    Raviraj A Bhedase
  2. 0
    Minhas Shaikh ·
    Thanks Raviraj.
    I have an other question

    After assigning resource budgeted and actual units . In resource usage profile graph, it shows budgeted , remaining unit curves but not "actual units curve". if we double click on graph it will give all values of budgeted, remaining as well as actuals . I also click on "resource usage profile options" .

    Thanks
    Minhas