Calendar by défault and specific calendar
In the Open Standard
Patricia Le ClaincheMember for 19 years 5 months
- Created
- 6
- 1
0
What happens if you use 2 different calendars in one project ; I mean :
=> In general, there is one Calendar which is put by default on each activity you create.
=> You can choose another calendar (with specific days Off, or vacations for example) for some activities.
In that case, what happens with Remaining Duration on the WBS Element ? It seems the remaining Duration is calculated with the Calendar by Default. Is it possible to change it for one or a few WBS elements of the project ?
I have not any "Calendar Column" in WBS view.
Hope to read you soon,
Regards.
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?