Hi Experts,

Can any one guide me - What is the dotted relationship line stands for in a layout. I know the red one is on Critical path and the balck ones are non critical. But I would like to know what these dotted ones stand for.

I would appreciate your advise on this. Thanks.
Rabbani

1 reply

Oldest first
  1. 0
    A D ·
    Hi rabbani,

    red lines shows the critical relationships.

    Normal lines shows the driving relationships

    Dotted lines shows the non-driving relationships.

    Thanks,

    Raviraj A Bhedase