Hi ,
How can I show constriant date on start or finish. My last actvitiy is going to finish on 5 Dec, 07. But we have to show 29th Nov 07 because its constraint. Can we show 29th November through constraint on start and finish columns instead of constraint column.
Can I fixed 29th November and get backward float.
Thanks
Minhas
How can I show constriant date on start or finish. My last actvitiy is going to finish on 5 Dec, 07. But we have to show 29th Nov 07 because its constraint. Can we show 29th November through constraint on start and finish columns instead of constraint column.
Can I fixed 29th November and get backward float.