Global change - Activty ID

Naveen SubbaiahMember for 21 years 9 months
Created
4
2
0
Hello people,

Can somebody suggest a method to change the first 4 characters in an activity ID using global change ? I am using P3e 4.1

Thanx in advance
Naveen

4 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Naveen,
    you can use the substring function of global change. It’s well described in the Help-Function - search, then enter "substring". But I’m not sure if this parameter already existed in 4.1.
    Regards

    Dieter
  2. 0
    Naveen Subbaiah ·
    Hi Dieter,

    Thanx 4 ur response. The substring funtion is helping me only in extracting the characters from the activty ID & not changing it. For exapmple, my activity ID’s are such as UTII-WWTC-0025, UTII-FG-0010 etc., Now in all these, I want to change UTII to UT2. The substring function is only extracting the first four character UTII !!

    Regards
    Naveen
  3. 0
    Dieter Wambach ·
    Hi Naveen
    after you extracted the not used values, try

    activity id = "abcd" & activity id to add the prefix "abcd"

    How to enter "abcd"?
    You click on custom in the selection window. Now you may enter any string.

    Regards

    Dieter
  4. 0
    David Forrest ·
    Select the first activity ID, Select Edit-Replace and type in the characters that you wish to change.