Baseline Variances

Rob MezgerMember for 19 years 8 months
Created
2
2
0
I am working in P5 and have been exploring varainces to baselines. I have a good understanding of how baselines work and I understand that P5 calculates variances to baselines using the early start and finsh dates. Does anyone know if it is possible to calaculate the variances based on the late start & late finsh dates instead?

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Rob
    There is no direct way.

    You can use a workaround - not elegant, but it works. Before you create a BL you move the late dates into UDF (User Defined Fields). Later you can compare with a global change and two more UDF.
    Ask your dealer to force Primavera to include the comparison of late BL dates into the standard.
    Regards
    Dieter
  2. 0
    Rob Mezger ·
    Thanks for the info Dieter - much appreciated,

    Rob