Baseline Variances
In the Open Standard
Rob MezgerMember for 19 years 8 months
- Created
- 2
- 2
0
I am working in P5 and have been exploring varainces to baselines. I have a good understanding of how baselines work and I understand that P5 calculates variances to baselines using the early start and finsh dates. Does anyone know if it is possible to calaculate the variances based on the late start & late finsh dates instead?
2 replies