Printing the calendar in P5

Kevin MatthewsMember for 20 years 3 months
Created
3
1
0
All,

In P3 there was a print button in the calendar dialog box; this has disappeared in P5. Any ideas how to print a caledar in P5. ?

Keep Planning,

Kevin.

3 replies

Oldest first
  1. 0
    Nigel Winkley ·
    There isn’t one! I asked the question of Primavera who seemed to think that this was a minor irritation. The nearest i have come is to create single activities and apply each calendar in turn to them then expand the timescale to suit with the bars necked.
    Pain in the whatsit I know.
    Cheers
    Nige
  2. 0
    Kevin Matthews ·
    Hi Nige,

    Maybe this ’issue’ will be solved with the new release.

    Thanks,

    Keep Planning.

    Kevin.
  3. 0
    Tim Readman ·

    Kevin & Nigel,  I have

     

     

    Kevin & Nigel,

     

     

    I have repeatedy asked Oracle /Primavera to ebale printing of calendars but with out success.

    In the end had get it produced by a programmer and it works.

     

    Try it out   at http://comviz.com.au/products/comvizcalendar/ 

    This is the blurb

    Comviz Calendar automatically calculates working days depending on the start day. These days do not include non-working days from Oracle Primavera P6 and the days marked as non-working. You can assign different colors and labels for the calendar days in order to create sofisticated calendars. 

     

    yes it used to be in P3 but we users are forgotten at times by our providers of the sofwatre

     