Introducing Change in P5

Oliver MellingMember for 19 years 5 months
Created
8
1
0
PP,

When a change is approved, what is the best way to introduce it into the P5 schedule?

Does the baseline programme need updating as well as the current programme (with new activities, resources expenses)?

8 replies

Oldest first
  1. 0
    Karim Mounir ·
    For me if a time claim is approved, then I revise the original baseline (eg. making rev. 1 from rev. 0), thus having two (or more) baselines attached to the updated schedule.
  2. 0
    Oliver Melling ·
    But how do you incorporate the additional time into the current plan?
  3. 0
    Karim Mounir ·
    U can use the As-built schedule and incorporate the additional activities in it or use the As-planned schedule and incorporate the additional activities in it (and later on update it to reflect the actual dates & progress % till the data date of the claim).

    Either can be used based on the method u adapt in getting the approval of the time claim (As-built vs. As-planned or Impacted As-planned...).

    Regards,
    Karim
  4. 0
    A D ·
    Hi Oliver, as karim has mentioned u can insert three types of activities into the new program:

    1. DELAYED EVENETS: All activities in which there is a delay impact by client and will straight way lead to increase in time of project.

    2. NEW PLANNED EVENTS: New change orders based on EI or PMI and can insert these new activities straight into the program

    3. MITIGATE EVENTS: All activities for which contractor can mitigate the impacted delays.

    Hope I am clear

    Cheers,

    Raviraj
  5. 0
    Oliver Melling ·
    Agreed changes to the baseline need adding as costed activities to the baseline programme. How do you then make sure they are in the as-built?

    By adding manually to the as-built, or by using som form of update function in P5?
  6. 0
    Karim Mounir ·
    After adding the additional activities in the baseline schedule u now have Rev. 1 of it, your As-built schedule should be having the same activities as of Rev. 1 of the baseline (Either u copy/paste Rev. 1 of the baseline schedule and use the copy as your As-built OR
    u add the additional activities manually to the As-built).

    After that u can use the update function in calibrating the assigned budgeted units between the baseline and the As-built schedule instead of doing it manually.

    Regards,
    Karim
  7. 0
    Oliver Melling ·
    Karim,

    As i understand it, you copy the revised basline programme, then import the current as-built programme into it as an update, thus changing it into the nrew as-built programme?
  8. 0
    Karim Mounir ·
    Right Oliver, this can be done.

    Regards,
    Karim

Log in or join to reply