Resources

Rajesh AnandMember for 19 years 10 months
Created
1
1
0

In P3
When I give the Resources from
Data
Resources
Mechanical Engineer

Limits
Normal Max
1 2

I want to know why we use 1 for Normal and maximum 2. Please do clarify my doubt? Please reply.

With Regards,
Rajesh

1 reply

Oldest first
  1. 0
    Mangesh Khuspe ·
    hi
    Rajesh its like that, if you want to assign a resource to any activity, it has to be atleast 1 in quantity, it cant be zero, if you want to spend money u have to have that, otherwise u cant spend.
    maximum u can give the no u want per day that is available.
    i.e. the limit that resource would be available on any particular day.

    cheers

    mangesh

Log in or join to reply