Change font properties

Susan YoungMember for 23 years 7 months
Created
3
2
0
Hello,

In P5, Is it possible to change the Font Color or properties of Activity description text for only 1 or 2 activities in a layout ?

If yes, can you please explain in detail how to do it ?

Thanks.

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Susan
    This is not possible.
    Dieter
  2. 0
    Andrew Podolny ·
    Hi Susan.
    I use the Adobe Acrobat Standard to highlight the certain activities after printing out to PDF.
    Regards,
    Andrew
  3. 0
    Susan Young ·
    Thanks,

    Can the contents of Notebook Topics be also shown in Activity Table as columns ?

    Sue