What is an S-Curve?

Chris AustinMember for 19 years 2 months
Created
2
5

2 replies

Oldest first
  1. 0
    Kevin Matthews ·
    Hi Chris,

    In planning terms a S Curve usually shows progress over time. The curve is usually shaped like a S because intially progress is slow, then ramps up in the middle of the project before levelling off at the end.

    All projects though do not follow the S curve format with some being more front loaded while others are back loaded; or even middle laoded (bell shaped curve)..

    keep planning,

    Kevin.