DETAILED MEANING OF LINES IN THE S-CURVE
In the Open Standard
Suresh Sankarankutty PMPMember for 20 years 3 months
- Created
- 2
- 16
0
Hi
I got some confusion in the S-curve. Could any one explain in detail the meaning and use of each line in the S-Curve.
In the S-Curve, the baseline , budgeted and actual curves are on issue. I just want to know clearly whats the Budget labout units line. As far as my understanding that is the requirement of the progress. If actual goes in parellel with budget it will reach on baseline on the specified date. Am i right ? is there any other meaning or something ?
Do we really need to show the budgeted line on the curve. Is it enough Baseline, Actual and Remaining curve lines.
Another thing i am looking for is . how can tell the difference between to curve lines in days or hours.
ie: Budget Labour Units - 1174.hrs, Actual Labour Units. 1100.hrs BL Budgeted Labour UInits-2869.
Basis on this how can findout howmany days i am behind or ahead schedule ?
Regards
Suresh
I got some confusion in the S-curve. Could any one explain in detail the meaning and use of each line in the S-Curve.
In the S-Curve, the baseline , budgeted and actual curves are on issue. I just want to know clearly whats the Budget labout units line. As far as my understanding that is the requirement of the progress. If actual goes in parellel with budget it will reach on baseline on the specified date. Am i right ? is there any other meaning or something ?
Do we really need to show the budgeted line on the curve. Is it enough Baseline, Actual and Remaining curve lines.
Another thing i am looking for is . how can tell the difference between to curve lines in days or hours.
ie: Budget Labour Units - 1174.hrs, Actual Labour Units. 1100.hrs BL Budgeted Labour UInits-2869.
Basis on this how can findout howmany days i am behind or ahead schedule ?
Regards
Suresh
2 replies
Oldest firstLog in or join to reply