Baseline bars DO NOT SHOW CORRECT DATES !!!

Sebastian RushMember for 22 years 2 months
Created
5
1
0
Hi All,

We have a 8500 plus activity network. We work on a remote server environment. THe schedule is based on WBS, but the grouping and sorting is done by activity codes. Multiple calendars are in use. Baseline has different data date (we have moved it since saving the baseline). We’re using P3e.

We assigned a baseline recently, but when displaying the bars, the visual duration of the bar in the gantt chart section does not represnt the dates we see on the Bl1 start and Bl1 finsih columns. This has us all puzzled, we can’t report our baseline, because it shows incorrectly.

Additionally in some cases, when you refresh (F5) the network, the baseline gets paired up with the current for only a few seconds until you click on the activity and the bar and dates return to its original date, this is not to bad, but if you don’t click on the activity it remains with the incorrect information, so, in reality unless you know what exact date to expect, you can’t know if the information is correct.

Has anyone experience this before or can anyone help me understand this strange behavior of P5e.

thanks.

5 replies

Oldest first
  1. 0
    K D ·
    Hi.
    You should go to View -> Bar. then check Timescale dropdown list to see whether it match with baseline you assigned.

    Thanks
  2. 0
    Luca Basile ·
    Hi
    Assuming you created and assigned a project as baseline and you are showing the right one (project, primary, etc...) I notice that P5 when is baselining is taking the dates from the planned start and finish fields.
    If these two are not alligned with the Start and Finish fields you may have funny results.

    Cheers
    Luca
  3. 0
    K D ·
    Hi Luca.
    Which date field the baseline take from is based on what timescale you choose.

    Current Bar: Represents the Start Date to Finish Date.

    Actual Bar: Represents the Actual Start Date to Actual Finish Date

    Remain Bar: Represents the Remaining Start Date to Remaining Finish Date.

    Plan Bar: Represents the activity’s Planned Start Date to Planned Finish Date.

    If you wanna compare to Start & Finish field ,you should choose Current Bar in Timescale.

    Thanks
  4. 0
    Pradeep Kumar Maharana ·
    Hi Guys,

    To solve this problem,

    Please go to
    1. Admin
    2. Select the Tab:- Admin Preferences
    3. Select the section :- Earned Value
    4. Please go to the bottom of the pop up under "When Calculating Earned Value from a baseline use":-
    select "AT COMPLETION VALUES WITH CURRENT DATES"

    This will solve your problem and you will get the correct date.

    Regards

    PK.
    PDO -Harweel project, Muscat
  5. 0
    Anning Sofi ·

    Pradeeps suggestion works.

    Pradeeps suggestion works.