Skip to content

Showing Driving Predecessors in layout/reports in p5

Maya CMember for 19 years 4 months
Created
3
3
0
In P3, we used to able to tell a DRIVING PREDECESSOR by the ASTERISK (*) marked next to the predecessor. That functionality seems to be lost in P5. Is there a way to show a driving predecessor in P5 layouts?

Thanks.

3 replies

Oldest first
  1. 0
    Paul Harris ·
    There are many things missing in Primavera Enterprise that are in P3, but thankfully Driving predecessors is not one of them.

    Display the Relationships form and right click below “Predecessors”, select “Customize Predecessor columns…” and display the “Driving” column.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Maya C ·
    Paul,
    Thanks for your comments.

    This solution works for the activity details section in the bottom of the schedule. However my question was if there was a way we can display that in the Predecessor column in a PRINTABLE layout.

    This is possible with P3, but lost in P3e.

    Let me know if I am making any sense.

    Maya
  3. 0
    Elena Secareanu ·

    I have filter for few

    I have filter for few activities but want also show their predecessors and successors. Using trace logic is for one activity only but want show group of activities ! Any help in how to set a filter in P6! Thanks

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?