Baseline of a Baseline
In the Open Standard
Mark ChapmanMember for 20 years 5 months
- Created
- 2
- 2
0
In P5, I have uncoupled my baseline only to find the baseline has a baseline which is different from the baseline plan. I go to Assign/Maintain Baselines and no baseline defined. I then go to summary tab/display dates and there are baseline dates which differ from the planned dates. So where is this baseline stored? Can I purge it?