Assign relationship faster
In the Open Standard
K DMember for 19 years
- Created
- 5
- 1
0
Hi all.
We have 1000 WBS. Each WBS has 1 level of effort activity. In this LOE activity, we need to assign predecessor to activity which start earliest in the WBS and assign successor to activity which finish latest in the WBS.
Could you suggest me a quickly way to do this? Assign manually for each LOE activity take lots of time.
Thanks & regards
Khuong
We have 1000 WBS. Each WBS has 1 level of effort activity. In this LOE activity, we need to assign predecessor to activity which start earliest in the WBS and assign successor to activity which finish latest in the WBS.
Could you suggest me a quickly way to do this? Assign manually for each LOE activity take lots of time.
Thanks & regards
Khuong
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?