Significance of EPS ,OBS in project?Does it impact on resources or its simply a for classifying project?
Other thing how we can allign EPS ,OBS,WBS & Cost Break Down structure?

3 replies

Oldest first
  1. 0
    Niek Zonneveld ·
    Imran,

    EPS is your WBS super structure and determines how you projects are grouped.

    OBS is the hierarchical PM structure in your organisation and is linked to access rights in combination with the EPS.

    Normally you don’t align EPS, OBS, WBS, and CAS because their are different structures that serve different purposes.

    H.T.H.

    Niek.
  2. 0
    John Raper ·
    To add to what Niek has outlined:

    The PROJECT is the LOWEST level in the EPS and the HIGHEST level in the WBS. It therefore sits between the EPS and WBS.

    HTH
  3. 0
    Imran Arshad ·
    Thanks John & Neik for your Kind supporting comments.