P6 on a Citrix Network

Oliver MellingMember for 19 years 5 months
Created
11
4
0
PPlanet,

My company is planning on moving 15 standalone P6 licenses

onto a server.

We need the ability to access P6 remotely and also want the

ability to use the web interface to show performance.

Does anyone have any experience of doing this? Is a seperate

web license necessary?

11 replies

Oldest first
  1. 0
    Imran Arshad ·
    Dear Oliver,
    You can access same license remotely.There is no need to buy a seperate License.
  2. 0
    Oliver Melling ·
    Imran,

    I think you can pay more for an un-named license, but i din’t think 15 planners could work on that license at the same time!
  3. 0
    Oliver Melling ·
    Imran,

    If i misunderstood your post then,I think a seperate license is required to post project info via a website dashboard on P6.

    Oliver
  4. 0
    John Raper ·
    Oliver

    I don’t think any new licence is need for using the web. We are about to upgrade stand alone P5 to Citrix enabled P6. This will give the option of accessing P6 from any company PC without it being installed locally.

    Hope this helps
    John (ex UK Nirex!)
  5. 0
    Dieter Wambach ·
    Hi Oliver
    as the licence is kept on the server it is independent from direct or access via citrix.
    When we upgraded from P5 to P6, some basic features of myPrimavera (or whatever name the web-based tool currently has) was included.
    Regards
    Dieter
  6. 0
    Imran Arshad ·
    Dear Oliver,
    I am using P6 directly & remotely with the same user name & password.
  7. 0
    Oliver Melling ·
    But you won’t be able to check files out during remote access i believe?
  8. 0
    Imran Arshad ·
    Dear Oliver,
    You can access every thing within P6 directly & remotely.
  9. 0
    Oliver Melling ·
    But can you check a project file out?
  10. 0
    Dieter Wambach ·
    Hi Oliver
    this is a question to your IT-staff.By standard, export/check-out goes to the local server - which is the Citrix-server. But this can be modified. Unfortunately I don’t know how to do it.
    Regards
    Dieter
  11. 0
    Imran Arshad ·
    Dear Oliver,
    Yes u can check out files remotely.when u linked with p6 remotely,u actually linked to main server which enables u to do things u want but as Dieter said it again depends on rights u have authorised from the IT-Staff.