When resch’ my Baseline milestones move along

Joel GilbertMember for 23 years 5 months
Created
1
3
0
This may have been dealt before,But I dont have time to read through all the Forums.

I’ve baselined my programm, now I update it, then I reschedule and I see my activities baseline dates stay as baselined but my milestones dont. they move along with the re-scheduled dates. What am I doing wrong? is there a way of saving the baseline. Note I am working on a 54 projects portfolio.

Any quick help welcomed.

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Joel
    Which timescale you selected for the baseline ms?
    It must be Primary Baseline, maybe you selected remaining.
    Cheers
    Dieter