SDK problem

Karim MounirMember for 20 years 6 months
Created
4
3
0
Hi,

I’m using the Excel files supplied with P5 to import/export data between Excel & P5.
I manged to export some UDF from Excel to P5 using these sheets, however when I tried to do the same for resource assignment I got errors at the end of process with the following desc.:
Row (all resource assigned act. rows): Invalid Value XoType:1 for column:start_date with XoType:11.

What is wrong?

Regards,
Karim

4 replies

Oldest first
  1. 0
    Johny Kesserwany ·
    Hi karim,

    The problem is with the cost account ID being blank. The SDK does not allow for a null value.
    Replace the existing Project.xls with the updated version.

    JK
  2. 0
    Karim Mounir ·
    Hi JK,

    I don’t actually how to get it, there is no cost account ID in the Resource Assignments sheet.
    The only columns found related to the cost are:
    BC, AC, RC, price/unit, Rate Type, Cost Units Linked

    Where should I put these cost account ID?

    Karim
  3. 0
    Johny Kesserwany ·
    It’s a primavera solution ID:prim13114.

    get there and download the updated excel file (project.xls).

    JK
  4. 0
    Karim Mounir ·
    thanks JK