How to export S-curve data to excel???

johar MishraMember for 18 years 8 months
Created
5
2
0
hi,
if you remember to export data from p3 we should go to reoprts\tabular reports\resources and set the interval (week/month) and generate a wk1 or db file and edit in excel ...
now the problem I faced is how to do the same in P5!
I export from "resource assignments" and copy and paste to excel, but I’d like to have a calculated early and late quantities (both) in excel at once.
any comments??
mp1j2000@yahoo.com

5 replies

Oldest first
  1. 0
    Mouneer Adel ·
    Hi there

    Open Reports and make a new report and choose time distrbuted data then activity resource assignments and then filter your required resources and when it comes to the time interval fields choose remainning early units & remaining late units , run report with the following options : ascii filed delimiter :tab text qualifier: none and choose the file name with xls extension and enjoy

    I hope that helps you

    Mouneer Adel
  2. 0
    johar Mishra ·
    Hi Mouneer,
    Thanks a lot for your help. I tried all options and got a lot of new points there, but I couldn’t find axact descriptions you told (remainning early units)!
    Could you please help me to find out this figure.

    Please have my e-mail as below: mp1j2000@yahoo.com
  3. 0
    johar Mishra ·
    OK,
    Thanks a lot. you had told every thing. solved.
  4. 0
    A D ·
    Hi Johar,

    U can try Pervasive ODBC drivers as well.

    I have never used P5, but works brilliantly on P3.1

    You dont need to perform these things with every update.

    If u use pervasive ODBC drivers (Free download available on net) then u need to just press the REFRESH button and it will be updated.

    Its far easy comapred to these things.

    Paper for the same can be found at Paul Harris (www.eh.com.au) website

    Cheers,

    Ravi
  5. 0
    Sahar Khoshsirat ·

    Weighted steps in primavera

    Weighted steps in primavera plan P6

     

    Hello

    Does any body know how weighted steps can affect my plan?

    Lets assume one activity has 4 steps, every step has its own start, finish and weight.

    I would like to schedule the plan and draw plan Scurve, but the weights and dates in steps does not affect my %schedule.

    Any help appreciated.

     

    Sahar