P6 - Problem Allocating Resources
In the Open Standard
Nicholas PorterMember for 19 years 8 months
- Created
- 2
- 2
0
When I allocate a labour resource to an activity, the didtribution of the activity occurs on each Monday.
eg Activity = Formwork, dur=6d
Resource = carpenter @ 10 units/day
Total units allocated = 60 units,
However P6 only allocates 30 units on two Mondays, not 10 units per day over the 6d duration.
I have reviewed my user preferences/options and can’t find anything obvious that would cause this issue.
Any advice would be appreciated,
Thanks
Nick
eg Activity = Formwork, dur=6d
Resource = carpenter @ 10 units/day
Total units allocated = 60 units,
However P6 only allocates 30 units on two Mondays, not 10 units per day over the 6d duration.
I have reviewed my user preferences/options and can’t find anything obvious that would cause this issue.
Any advice would be appreciated,
Thanks
Nick
2 replies
Oldest firstLog in or join to reply