Skip to content

P6 - Problem Allocating Resources

Nicholas PorterMember for 19 years 8 months
Created
2
2
0
When I allocate a labour resource to an activity, the didtribution of the activity occurs on each Monday.

eg Activity = Formwork, dur=6d
Resource = carpenter @ 10 units/day

Total units allocated = 60 units,

However P6 only allocates 30 units on two Mondays, not 10 units per day over the 6d duration.

I have reviewed my user preferences/options and can’t find anything obvious that would cause this issue.

Any advice would be appreciated,

Thanks

Nick

2 replies

Oldest first
  1. 0
    Anoon Iimos ·
    have a look at your calendar (resource calendar or activity calendar) and working hours; holidays; non-working hours
  2. 0
    Waseem Saber ·

    Check the calender, it is possible your setting is set for 50% usage, i,e you get 30 instead of 60.....

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?