showing relationships

Prem Kumar,Member for 21 years 7 months
Created
3
4
0
hi

When you show, target and current bars in gant chart view, how to show the releation ships line between the current bars. mine is showing the relationship for the target bar

regards

prem

3 replies

Oldest first
  1. 0
    James Shimmon ·
    right click in the gantt chart view and shift the Primary baseline bar and primary milestones down to the bootom of the list,should sort it out. Quirk of the system!!!
  2. 0
    Prem Kumar, ·
    Thank you very much.

    where did u get it, is there in the primavera manual?

    regards

    prem
  3. 0
    James Shimmon ·
    no, it is just something I found out when I was experimenting because I had the same problem