Imprting baseline
In the Open Standard
Natasha JuckesMember for 18 years 7 months
- Created
- 4
- 1
0
Our company have upgraded to P6 yesterday from P3e 4.1 and I am experiencing a couple of minor problems, as follows:
1. I am trying to make a global change however I cannot select the ’BL Project Early Finish’ field from the displayed list. I can only select ’Project Finish’. Is there a way of importing this column heading so it can be used?
2. When I import a baseline, either by converting the current project or by saving a copy of it as a separate project and importing it as a BL, the start and finish dates of the imported BL change and display old dates, which may have been used as data dates or past dates from many months ago. How do you import a BL without it using old redundant dates?
1. I am trying to make a global change however I cannot select the ’BL Project Early Finish’ field from the displayed list. I can only select ’Project Finish’. Is there a way of importing this column heading so it can be used?
2. When I import a baseline, either by converting the current project or by saving a copy of it as a separate project and importing it as a BL, the start and finish dates of the imported BL change and display old dates, which may have been used as data dates or past dates from many months ago. How do you import a BL without it using old redundant dates?
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?