Calculation of activity duration ???????????????
In the Open Standard
Andrew DickMember for 19 years 8 months
- Created
- 16
- 2
0
While doing some analysis of our construction program, I have drawn the following conclusion;
I’m Confused…….
I have 1 activity on a 9 hr/day calendar (7:30 – 4:30), 10 days in duration. The activity starts at 0730 on the first day and finishes at 15:30 on the 9th day. This is some 1 day 1 hour early.
What I reckon is that we say we are able to work for 9 hours each day and the system default is 8 hrs per time period.
Therefore the planned 10 days * 9H/d = 90Hrs duration is calculated at 8H/d for 10 days based on a 9hr/d calendar therefore giving an early finish equal to 10 hours early. I.E 9th day at 15:30Hrs.
Now how do you reckon this will extrapolate over a 2 year construction program that is working on a construction calendar equal to 7 days/week 9 hrs/day when as far as Primavera is concerned all durations and therefore end date is calculated based on 8Hr/d, 40Hr/W, 172Hr/M, 2000Hr/Y. When what we’re saying is we need 9H/d, 63H/w, 273H/m, and 3276H/y less Easter and xmas break.
Has anybody else confirmed this??
How do I fix it??
Have I grabbed hold of the right end of the bull??
I don’t have access to the global admin settings.
Andy
I’m Confused…….
I have 1 activity on a 9 hr/day calendar (7:30 – 4:30), 10 days in duration. The activity starts at 0730 on the first day and finishes at 15:30 on the 9th day. This is some 1 day 1 hour early.
What I reckon is that we say we are able to work for 9 hours each day and the system default is 8 hrs per time period.
Therefore the planned 10 days * 9H/d = 90Hrs duration is calculated at 8H/d for 10 days based on a 9hr/d calendar therefore giving an early finish equal to 10 hours early. I.E 9th day at 15:30Hrs.
Now how do you reckon this will extrapolate over a 2 year construction program that is working on a construction calendar equal to 7 days/week 9 hrs/day when as far as Primavera is concerned all durations and therefore end date is calculated based on 8Hr/d, 40Hr/W, 172Hr/M, 2000Hr/Y. When what we’re saying is we need 9H/d, 63H/w, 273H/m, and 3276H/y less Easter and xmas break.
Has anybody else confirmed this??
How do I fix it??
Have I grabbed hold of the right end of the bull??
I don’t have access to the global admin settings.
Andy
16 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?