Update schedule through Excel
In the Open Standard
KD
K DMember for 19 years
- Created
- 14
- 5
0
14 replies
Oldest first- 0DWDieter Wambach ·Hi
This process is basically the same as in P3.
1. Create an export with the data you want to update.
2. Select the groups you want to update: activities in any case, may be + relationships or assignments.
3. The export file will create an EXCEL-file with one table for each group.
4. You’ll modify the data or add new records
5. Import
6. Modifications will be updated in the project, new records attached.
Until now I couldn’t find any mistake, but did not check to create new resources by import - there first was a bug in P5 or delete records.
You must not modify the structure of the EXCEL-file.
We use P6.
Regards
Dieter - 0DWDieter Wambach ·Hi Jerry
I didn’t have this problem and I never heard of it. There is no explanation. We use P6.
Did you run "check project integrity" (unter Tools)?
Did you empty the column WBS-Code in EXCEL. Was in addition "hide if empty" selected und "Group & Sort"? There might be the reason because as far as I know the import doesn’t touch the WBS.
What did the hotline support say?
Regards
Dieter
- 0DCDang Corp ·Hi there,
If you really want to save time in updating the plan,
I find the built in import/export quite cumbersome and not straight forward.
You might want to consider using the ToolBox
i am currently using it nearly everyday, and once you discover, how it can easily import data,
assign codes etc... you will never turn back again.
http://www.dangcorp.com/toolbox.aspx
don’t think this is a sale pitch, just want to share my trade secret so that our industry doesnt waste time in data-entry, beacuse it saves me heaps of time,
giving me more time to analyse the plan,
because the place i am working now, we get heaps of data from managers, and no time to enter them. :) as usual!
so we use it practically daily. for all kind of purpose ok.
Vu Dang
- 0DCDang Corp ·HI K D,
I dont think it is expensive, hehe
i can assure you, in the first few days of its usage, it pays for itself...
it loads all the data for you, leaving u time to do more important things, such as get ur plan right.
and stream lining it, re-programming it to meet ur deadline,
so u can finish ur project earlier etc...
i think that is valuable tool,,, it already saving u in hiring a clerk to enter data.
- please try out the software from the website and let me know your opinion. cause i think it is useful for everyone!
Vu Dang
www.dangcorp.com - 0DCDang Corp ·Hi K D,
thanks K D, try out best to make it simple yeah.
I totally understand your comment,
I experience the same first impression as u too mate,
but once the company seen what it can do,
they convince themselve, as in ,,, if a company that is using Primavera, the project they managing are in not little baby projects, its massive,,, and with massive projects comes high risk if late and so on...
so instead of monthly report, which i know most company do, due to lack of resource in punching in data, etc...
u can do it in bi-weekly, etc...
in summary
----------
i dont think the costs is the issue, 2000 is small potatoes for any project that is already using primavera.
its more of like, they see it first, and they are convince themselves...
Hopefully it can reach VN one day.
======================
?
K D, u can purchase it globally.
Vu Dang
- 0JLJerry Lan ·Hi Dieter,
I tried to export into excel and import as an exercise. It did not touch the WBS this time,if I do not ammend the excel file at all. I will post into another thread what I did if it happens again. Let’s try to solve KD’s problem in this thread...yes you are right KD..using the SDK seem to be problematic too...I often get errors when clicking "Set" button....The "Get" button works well...