EDITING ACTID Column in PREDECCESSOR BOX-P6

Waseem SaberMember for 21 years 10 months
Created
1
3
0
i am not able to edit the ACTID column in the predecessor box, this was possible in P5, i was able to cut & Paste the ActID’s, this was a very handy way to get the linking of relationship quickly... is this a problem curable? are there any similar concerns, lets share it,please.......



regards

waseem saber

1 reply

Oldest first
  1. 0
    Salahuddin Ahmed ·
    Waseem,

    Well what I understand is you are asking how to edit Activity ID in predecdssor box.

    > Click on activity where you want changes
    > Open activity detail
    > Double click on ACT ID
    > Edit as required

    Thanks

    Salah