Cross-project Interfaces

Dave RodwellMember for 25 years 2 months
Created
3
3
0
I have a number of immature projects that when fully developed will have interfaces to other deliverable dates within the suite. The interface points are likely to be milestones. Thus far I am struggling to achieve a link.

All suggestions will be very welcome.

3 replies

Oldest first
  1. 0
    Dave Rodwell ·
    So now I can answer my own question.

    Simply open the relevant projects, select a source milestone in project 1, select a destination milestone in project 2 and check the assign box.

    Very easy.
  2. 0
    Luca Basile ·
    At any time you can also run a report in Primavera Enterprise to show only the interprojects links going out from one project

    Luca
  3. 0
    Dave Rodwell ·
    Thanks Luca, that’s a good tip, I shall try it once I have established the interfaces.

    Regards

    Dave