p5 tp p3

Kier LegardMember for 20 years 2 months
Created
2
1
0


Hi to all,


I created a program in p5 and then exported it to p3. After export some of my wbs is missing.Our clients wants the program in p3.

Has any onyone encountered this before?

Regards,

kier

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Kier
    Was it for empty wbs? Just an idea: if you import from P3 there is a check-box "include empty wbs". May be if you mark it and then start the export to Ps it might work. But it’s just an idea.
    Good luck!
    Dieter
  2. 0
    Dieter Wambach ·
    Kier
    Just found that empty wbs are not exported.
    Dieter