Hi:
I used P3 for the last ten Years and I’m migrating to P5,
I reserve my opinion about P5, maybe a need to be more familiar with this software to understand it better.Y need to create the Graphic reports for the resources By Craft or discipline somebody can tell me how?

5 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Armando
    View --> Show on bottom --> Resource Usage profile --> "F1"-Key (Help) --> click on "Resource usage profile" and you’ll be guided.
    Left from the profile you can select Role (=discipline) or Resource, then just try until you’ll see what you need.
    Print: File --> Print preview --> Walk through the detail tabs. "Apply" will show you the result of your adjustments without leaving the function.
    Dieter
  2. 0
    Amanullah Mughal ·
    Dieter,

    What do y mean "from left select profile discipline or resource" IT DOES NOT WORK; Please explain.

    aman
  3. 0
    Amanullah Mughal ·
    I got it.

    Thankx.

  4. 0
    Dieter Wambach ·
    Aman
    My text was different.
    But to explain it in a different way: Resource usage profile window has four quarts. Upper left: Activity table, Upper right: Bar chart, lower right: histogram (or spread-sheet), and lower left the resources or roles. on top of this screen (lower left) you see "display" --> mouse click --> select view --> "Role" or "Resource" what ever you want. This should work now.
    Read the help text
    Regards
    Dieter
  5. 0
    Armando Ugarte ·
    Hi Dieter:
    I got it thank you very much for you help

    Armando