Replacing resources
In the Open Standard
Yusuke KamuiMember for 18 years 5 months
- Created
- 10
- 7
0
Hi,
I want to replace a resource (John Doe) from my schedule but P5 is not allowing me. The error message says "the current resource has actuals"! John Doe left the company and he will be replaced (including all his balance units/work) to someone. Take note John Doe was assigned and having actuals to more than 100 activities.
I want to retain the actuals that John Doe had in the schedule and not simply delete John Doe plus his past actuals.
How to do it?
Thanks.
I want to replace a resource (John Doe) from my schedule but P5 is not allowing me. The error message says "the current resource has actuals"! John Doe left the company and he will be replaced (including all his balance units/work) to someone. Take note John Doe was assigned and having actuals to more than 100 activities.
I want to retain the actuals that John Doe had in the schedule and not simply delete John Doe plus his past actuals.
How to do it?
Thanks.
10 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?